Renovation Update

posted Oct 4, 2016, 4:13 AM by Legion Webmaster
The progress of the Canteen Renovation is moving along rapidly. As of recently the new drywall is complete, the electrical inspection passed, the drains have been moved and complete, the AC is complete and half of the inside roof has been painted to be finished today.  This includes all the AC duct work.  The floor will be started Friday the 7th and the room will be completely closed for 4 days.  The new bar stools will arrive on the 21st and we will need a team to unload and assemble them. The new bar is being built at this time and will be assembled in place after the floor is complete.